You know its summer time in New Orleans when it rains almost everyday. We don't complain though since it helps bring down the temperature to help cool off what usually begins as a hot and humid day.
This week we began putting primer on the walls as we are preparing to start painting in just a few weeks. We are at that point of starting to see some of the light at the end of the tunnel. We do have a few big things that we are currently working on that need your prayer and possibly your assistance.
Our current list:
- Roof insulation to be completed
- Fire suppression plans to be completed and pipes to be arranged
- HVAC duct work assembly and completion
- Drop ceiling materials and installation
- Interior doors/windows/outlets/base cove to be installed
- Flooring? Tile vs. Stained concrete
- Phone system and fire alarm
- Glass front doors
- Wheel chair ramp
- Completion of stucco